TODAY.AZ / Business

Concreting works implemented in Sheki module power plant

11 April 2006 [09:08] - TODAY.AZ
Concreting works are underway in the Sheki module power plant which is currently being constructed.

As APA informs quoting the director of the ASES Company of Azerbaijan Nazim Garayev, concreting of the foundation has already been completed.

Brigades of the AZENCO Company and Mingechevir power unit were also involved in construction works in the power – here they are implementing installation and assemblage of equipment, construction of cables, insulation works and etc. taking into account high intensity of works, the labor protection service of Azerenergy conducted one-day workshop at the building site with the participation of the subcontractor.

Recommendations were given on avoiding industrial injuries, precise mutual cooperation of separate brigades, and application of technological cards to ensure consistency of the work. Besides, instructional advices were provided on aiding at the scene of the work, prophylactics of industrial injuries and reduction of injury cases.

Analogous measures are planned to be conducted during construction of module power plants in Kachmaz, Nakhchivan and Baku as well.

URL: http://www.today.az/news/business/24995.html

Print version

Views: 2345

Connect with us. Get latest news and updates.

Recommend news to friend

  • Your name:
  • Your e-mail:
  • Friend's name:
  • Friend's e-mail: