According to Trend, this place earlier chosen for construction of the module power station turned out unsuited after survey and other 10-hectare place at 15 km of the Nakhchivan-Julfa main line was chosen.
The head of Azerenerji has got familiar with the construction of the gas turbine station. To this date the 1st and the 2nd energy units have been launched at the station. The specialists test gas pressure regulation system acquired from Holland. They are currently working on launching of 2 other energy units.
The station will be put into exploitation till late April. It will allow the Company to improve energy supply of the Nakhchivan AR.