TAP introduces first natural gas into Greek section

26 November 2019 [16:28] - TODAY.AZ

By Trend


On 25 November, the Trans Adriatic Pipeline (TAP) AG started to introduce the first natural gas into a 2 km section of the pipeline in Greece between the Evros river and the Kipoi compressor station, Trend reports citing the TAP AG consortium.

“This is the initial stage of the pipeline commissioning process, which aims to ensure that the infrastructure is entirely safe and ready for operations after the completion of the process, in line with national and international safety and operational standards,” reads the message.

Ricardo Ruiz Nuñez, Operations Director for TAP, said: “Safety is our number one priority and we have prepared thoroughly for this important step. We are starting the introduction of natural gas into the system in line with our commitment to safety, environment and quality standards. TAP implemented a Start Up Readiness Assurance Programme which verified that all aspects of construction, commissioning, start-up and business requirements were in place prior to the introduction of natural gas. Our Operational Readiness Programme ensured that our staff and contractors were fully trained prior to the commencement of this important activity and will continue to be our foundation as we bring gas further into Greece and beyond.”

John Haynes, TAP Project Director, said: “More than three and a half years since the start of construction, 46 million man-hours worked safely and 128 million kilometres driven without any major incidents, we are pleased to have the pipeline system progressively ready for the complex commissioning phase. We would like to thank our network of contractors, subcontractors and partners who have shared our commitment to safety and high industry standards and who contributed to TAP reaching this important milestone.”

TAP project, worth 4.5 billion euros, is one of the priority energy projects for the European Union (EU). The project envisages transportation of gas from Azerbaijan's Shah Deniz Stage 2 to the EU countries.

Connecting with the Trans Anatolian Pipeline (TANAP) at the Greek-Turkish border, TAP will cross Northern Greece, Albania and the Adriatic Sea before coming ashore in Southern Italy to connect to the Italian natural gas network.

The project is currently in its construction phase, which started in 2016.

Once built, TAP will offer a direct and cost-effective transportation route opening up the vital Southern Gas Corridor, a 3,500-kilometer long gas value chain stretching from the Caspian Sea to Europe.

TAP shareholders include BP (20 percent), SOCAR (20 percent), Snam S.p.A. (20 percent), Fluxys (19 percent), Enagás (16 percent) and Axpo (5 percent).

URL: http://www.today.az/news/business/188612.html

Print version

Views: 890

Connect with us. Get latest news and updates.

Recommend news to friend

  • Your name:
  • Your e-mail:
  • Friend's name:
  • Friend's e-mail: