The oil will be pumped from Azeri oil field to Sangachal terminal oil tanks for three weeks; filling of Azerbaijani part of the pipeline will take 1,5 months, Georgian Part - 1 month, Turkish part - 2-2,5 months.
To avoid the loss of time the process will begin as soon as construction works end in Turkey.
10 million barrels needed to fill BTC pipeline
Ten million barrels of oil will be needed to fill Baku-Tbilisi-Ceyhan pipeline, and this process will take five months.