STEP Phase 3 to be complete in June

16 March 2007 [08:15] - TODAY.AZ
The Sangachal Terminal Expansion Programme (STEP)-Phase 3 main construction works are progressing well and are currently 88% complete, said the Project Manager Norman Ingram.

He said the activities have to date spent approximately $107m, adding that the pipelay is complete and power lines construction is under way. The Phase 3 is expected to be completed in June and will be brought online after trial in the fourth quarter of 2007. APA-Economics